PROJECT DESCRIPTION

HIGHLIGHTS

  • Asbestos and Lead Surveys
  • Soils investigations and preparation of geotechnical reports
  • Underground Site Scanning by utilizing Ground Penetrating
  • Radar (GPR) and Magnetometer Scan Techniques
  • Provided complete A/E Services
  • Received a Merit Award in the Concept Design Category of USAFE Design Awards Program 2004.
  • The aim of the project was to generate whole A-E services to avail the construct. of a 2.150 m² Consolidated Communications Maintenance and Administrative Facility. The building was designed to be a reinforced concrete structure complete with pavements, site work, security systems, fire prevention/alarm systems, utilities, force protection measures.
  • The building consisted of a ground floor, a first floor and a partial basement. The building was constructed to be adjacent to the existing Fac. No. 476 and physical connections were provided between the cable vaults and switch rooms. The construction of the building is completed.


Design Completion Year : 2006

Client : USACE Europe District